Eagle Drive

Status: Complete
Project Info
Work Order #: 
I-19-W-URG
Category: 
Releasing Department: 
Capital Planning and Resiliency
Effective Date: 
Monday, January 4, 2016
Completion Date: 
Friday, January 20, 2017
Files
Events

No events have been scheduled for this project.

General Description: 

Replacement of Eagle Dr. from SW 19th to SW 14th street with the addition of sidewalks and a gateway sign for the Foxglove housing addtion.

Vendors

Rudy Construction

Maximum Contract Price: 
$723,658.84
Procurement Narrative: 

A City Bid announcement was made on October 9, 2015 for City of Moore Public Works On-Demand Construction Services. Bids were accepted until October 30, 2015 and five submittals were received. Rudy Construction was awarded the contract on November 16, 2015.

Veolia

Water meter relocation

Maximum Contract Price: 
$3,800.00

Project Updates

The water line replacement is complete along Eagle Dr from SW 19th to SW 14th street. Curb and Gutter is complete on the west side of Eagle Dr.