S. Broadway

Status: Complete
Project Info
Work Order #: 
I-14-E-URG
Category: 
Releasing Department: 
Capital Planning & Resiliency
Effective Date: 
Monday, March 21, 2016
Completion Date: 
Friday, January 20, 2017
Files
Events

No events have been scheduled for this project.

General Description: 

Street repair and replacement from SE 19th St to SE 4th St, drainage work, and waterline replacement and relocation.

Vendors

Silver Star Construction

Maximum Contract Price: 
$ 3,154,484.14
Procurement Narrative: 

A City Bid announcement was made on October 9, 2015 for City of Moore Public Works On-Demand Construction Services. Bids were accepted until October 30, 2015 and five submittals were received. Silver Star Construction was awarded the contract on November 16, 2015.

Veolia

Water line relocation and replacement

Maximum Contract Price: 
$562,130.00
Procurement Narrative: 

A City Bid announcement was made on August 12, 2015 for Operations, Maintenance, and Management Services. Bids were accepted until September 11, 2015 and five submittals were received. Veolia Water North America was awarded the contract on December 21, 2015.

Poe & Associates

Maximum Contract Price: 
$238,150.00
Procurement Narrative: 

A City Request for Proposal announcement was made on May 13, 2015 for Civil Engineering Services for Disaster Recovery. Proposals were accepted until June 4, 2015 and 23 proposals were submitted. The following firms were selected:
1.Meshek & Associates
2.Poe & Associates
3.Cabbiness Engineering
4.CEC Infrastructure Solutions

Project Updates

Contractor finished the added items to the initial punch list that was issued. A few more areas needing slab sod were covered and some manhole aprons were poured and final cleanup done.

Project: 

Project was substantially complete through end of November with final walk through completed on December 9th 2016.

Project: